No | Customer | Description | End date |
---|---|---|---|
1 | Consolidated Power Projects | 220 kV Ring alongside Nairobi | December 2018 |
2 | Kenya Electricity Generating Company Limited (KenGen) | Kamburu power station remedial works | October 2017 |
3 | Jianxi Water and Hydro Company A/C Kenya Tea Development Agency Power Co. Ltd | Erection & commissioning of 5.4MW North Mathioya (3×1.8MW units). Design of four substations for KTDA factories interconnections (Kiru, Gatunguru, Kanyenyeini & Githambo tea factories) and of 33kV transmission line from power house to the 4 factories & interconnecting it to Githambo KPLC substation. | September 2017 |
No | Customer | Description | End date |
---|---|---|---|
1 | Hexing Electrical Co. Ltd | Supply, Installation and commissioning of Large power customer metering solutions | November 2017 |
2 | Andritz Hydro A/C KenGen | Kindaruma additional works:- Intake roller gates and embedded parts assembly. | October 2017 |
3 | Kenya Electricity Generating Company Limited (KenGen) | Sand blasting and painting of Kindaruma machine 1 and 2 spiral casing, guide vanes, stay vanes. | September 2017 |
4 | Kenya Power & Lighting Company (KPLC) | Design, Installation and commissioning of additional power transformers at existing substations (Gigiri, Cianda & Steel Billets 66/11KV substations) | June 2017 |
5 | Kenya Power & Lighting Company (KPLC) | Design, Supply, Construction, Testing and Commissioning of 1x 7.5 MVA , 33/11kV substation and associated 33kV & 11kV lines in Lamu | April 2016 |
6 | Hexing Electrical Co. Ltd Account Kenya Power | Installation and commissioning of AMI smart meters with data concentrators 3,300 meters | March 2017 |
7 | Hexing Electrical Co. Ltd Account Kenya Power | Installation and commissioning of Large power customer metering solutions, 5410 meters | March 2017 |
8 | Consolidated Power Projects (CONCO) RSA. | KPLC Project in Kainuk Complete Civil and electro-mechanical installation works, 1×45 MVA Power Transformers capacity 220/66/11 kV Substation, including pre-commissioning tests. | December 2015 |
9 | Shyama Power | Civil works for Konza 132/33 kV, 1×23 MVA substation | October 2015 |
10 | Shyama Power | Civil works for Namanga 132/33 kV, 1×23 MVA substation | October 2015 |
11 | Larsen & Toubro Ltd India | Completed Electro mechanical work including commissioning for 66/11kV 5MVA substation | March 2015 |
12 | Siemens Limited | Erection and commissioning of 220kV Suswa substation Complete installation of 12 diameter of 1 ½ breaker scheme 220 kv 50 MVA, 220 kv reactor | November 2014 |
13 | Consolidated power projects (Pty) ltd | KPLC project – Thika industrial. Complete electro-mechanical installation works, 2×45 MVA power transformers capacity 66/11 kV substation, including pre-commissioning tests | November 2013 |
14 | Andritz Hydro | Kindaruma implementation of 3rd unit and rehabilitation | July 2013 |
15 | Andritz Hydro | Rehabilitation of governors and control equipment at Masinga power station | December 2012 |
16 | Kenya Power & Lighting Company (KPLC) | Complete erection and installation of new 132 kV sub-station equipment Extension of existing 220/132 kV substation, gas and fire detection systems, station auxiliaries, control and power cables lying, termination & transmission line works | June 2011 |
17 | Moi international airport, Mombasa | Replacements of 15 no’s 11 kV switch gear panels and 2 nostrum; installation, testing and commissioning | Feb 2009 |
18 | BWSC via Burhani engineers limited | Complete erection and installation of new 132 kV sub-station equipment Extension of existing 220/132 kV substation, gas and fire detection systems, station auxiliaries, control and power cables lying and termination. | March – Oct 2009 |
19 | Kenya Power & Lighting Company via AREVAT & D Subcontractor | Installation of 33/11 kV switchgear and power transformers at Kipevu, Bamburi, Miritini, Diani, Voi and KPRL substations in Mombasa | February 2009 |
20 | Kenya Revenue Authority, via contractor | Repair and maintenance of 11kva oil circuit breaker | March 2008 |